How much material for a 3×3 m suspended ceiling (9 m²)
A 3×3 m space has 9 m² of ceiling and 12 m of perimeter for the wall angle. Below is how much runner, hanger and 600×600 tile that grid takes.
Grid and tiles
Layout 3 × 3 m. Mains: edge ≤0.6 m, spacing ≤1.2 m → 3 rows × 3 m = 9 running m, 3 lengths (profile reserve 10%). Hangers: 3 rows × (3 ÷ 1.2 + 1) = 12 pcs. Cross tees estimated by area.
Start marking the frame from the centre of the ceiling so the trimmed tiles at opposite walls are equal in width — the ceiling looks symmetric.
600×600 mm (2′×2′) tile, exact layout: main runners at 1.2 m (4 ft) centres, no further than 0.6 m from the wall, hangers every 1.2 m (4 ft) along each runner. 3.6 m (12 ft) main runner stick, 150 mm drop, concrete soffit, rod hangers. 10% allowance on tiles and 10% on the grid. Light fittings, air grilles and access hatches are not included — each one hangs on its own hangers.
If yours differs — open the calculator and change the dimensions, it will recalculate.